PCMC begins construction of two roads to airport
TNN | Updated: Mar 29, 2018, 10:00 IST
Source : The Times of India
TNN | Updated: Mar 29, 2018, 10:00 IST
Pimpri Chinchwad mayor Nitin Kalje said, “People from Pimpri Chinchwad have to travel via Pune-Alandi road, Vishrantwadi and Tingarenagar to reach the airport now. However, after the completion of the two roads in Charholi, people can bypass Pune-Alandi Road and reach the airport quickly. The new roads will also help people reach Markal and other industrial areas outside the city without visiting Alandi.”
He said the road is expected to be completed by July end next year. “The work is in progress on the second road, which will be 30-metre wide, from Patharemala to DY Patil college. The length of this road is 2.640km. The road is expected to be completed by end of January 2020. The total expenditure is Rs 35 crore.”
Source : The Times of India